RM of Frenchman Butte No. 501 - Tender for Road Construction - Winkler Road -- ST205011
The Rural Municipality (RM) of Frenchman Butte No. 501 is reconstructing approximately 1.75 km of Winkler Road, East of St. Walburg, SK. The Project is located on the East edges of NE 33-53-22 W3M and SE 04-54-22 W3M in the RM of Frenchman Butte.
The Project will be completed to reconstruct the road surface, replace outdated infrastructure, allow the roadway to meet both current and future traffic needs as well as to maintain surface drainage across the Project extent.
Road reconstruction activities across the Project extent will include expanding the Project right-of-way (RoW), upgrading the road top, side slopes and ditches, widening and straightening the road, raising the grade of the road, replacing all existing culverts, installation of new culverts, improving existing approaches, back sloping and surfacing. Surface drainage patterns will be maintained across the Project extent as part of the design and construction practices. Construction materials will include clay sourced from outside the RoW and a borrow area located in NE 33-53-22 W3M.
No additional information for this competition.
|
Nov 23, 2020 11:01 AM CST
|
|
Nov 02, 2020 07:00 AM CST
|
|
Nov 23, 2020 11:00 AM CST
|
Aaron Neilly
306-344-2034
rm501cet@sasktel.net
R.M. of Frenchman Butte No. 501
Box 180
Paradise Hill, SK, Canada
S0M 2G0
306-344-4434
Competition Information
Closed
|
ST205011
|
Rural Municipality of Frenchman Butte No. 501
|
RM of Frenchman Butte No. 501 - Tender for Road Construction - Winkler Road
|
Invitation to Tender
|
No
|
The Competition detail was successfully retrieved. Jul 05, 2025 04:39 PM CST