Roadwork-CONSTRUCTION OF A SHORT SPAN BRIDGE on Hwy 120 over Torch River CS120-02 near Candle Lake -- HWY-B23062
CONSTRUCTION OF A SHORT SPAN BRIDGE on Highway No. 120 over Torch River at C.S 120-02 Km 9.77 near Candle Lake, Saskatchewan, with a new bridge.
Bidders shall submit all inquiries pertaining to the Bid Package documents a minimum of 3 business days prior to close of bidding directed to:
Ministry of SaskBuilds and Procurement
RFXquestions@gov.sk.ca
Bidders may request a debriefing session from Ministry of SaskBuilds and Procurement by emailing constructionsbp@gov.sk.ca within 30 days after the award notification date. The intention of the debriefing is to aid the Bidder by identifying areas of improvement that may be applied to subsequent procurement opportunities.
Estimated Quantities:
Design, Construction, Maintenance And Removal Of A Temporary Detour: lump sum
Supply And Installation Of Sheet Piling: lump sum
Supply Of Piling: 336 (m)
Mobilization: lump sum
Completion Date: June 30, 2024
Deposit with each Tender - 5% of total bid.
Deputy Minister of Highways
Award Documents:
Award Details
Harbuilt Construction Management Ltd.
Moosomin, SK
$1,672,253.50
Nov 28, 2023
Harbuilt Construction Management Ltd.
|
Moosomin, SK
|
$1,672,253.50
|
|
Nov 28, 2023
|
|
Nov 28, 2023 04:08 PM CST
|
|
Nov 06, 2023 10:45 AM CST
|
|
Nov 21, 2023 02:00 PM CST
|
Tina Munro
RFXQuestions@gov.sk.ca
Ministry of SaskBuilds and Procurement
submission@gov.sk.ca
Competition Information
Awarded
|
HWY-B23062
|
Highways
|
Roadwork-CONSTRUCTION OF A SHORT SPAN BRIDGE on Hwy 120 over Torch River CS120-02 near Candle Lake
|
Invitation to Tender
|
No
|
The Competition detail was successfully retrieved. Sep 13, 2024 10:52 PM CST