Frontier School Day Care Acoustical Treatment -- CSD-Frontier-2020
Install new STC rated walls and acoustical ceiling tiles along the inside of the existing walls of the daycare, and extend existing mechanical and electrical items to face of the wall at Frontier School - 208 1st Street East Frontier, SK.
Site walk through is scheduled for Tuesday March 18, 2020 at 3:30pm.
Contract completion date - July 13, 2020 contractor to receive access to the space. August 7, 2020 contractor is complete.
Award Documents:
Award Details
D.W. Wallace Construction
Swift Current, SK
$24,770.00
Apr 06, 2020
D.W. Wallace Construction
|
Swift Current, SK
|
$24,770.00
|
|
Apr 06, 2020
|
|
Apr 14, 2020 09:52 AM CST
|
|
Mar 12, 2020 08:20 AM CST
|
|
Mar 27, 2020 10:00 AM CST
|
Ward Peters
306-721-1080
ward@1080architecture.com
1080 Architecture, Planning and Interiors Ltd.
office@1080architecture.com
Competition Information
Awarded
|
CSD-Frontier-2020
|
Chinook School Division No. 211
|
Frontier School Day Care Acoustical Treatment
|
Invitation to Tender
|