Request for Supplier Qualifications for Lac La Ronge Dam Seepage Remediation -- WSA-2019-0112
The overall objective of this project is to construct a seepage cut-off wall to eliminate the flow of water through the Lac La Ronge Dam Embankment. The construction of the seepage cut-off wall will involve driving sheet piles to form a wall through the embankment, and injecting grout at low pressure to form a grout curtain. It may be noted that the top-ranking respondents from this Request For Supplier Qualifications (RFSQ) will be required to complete a mandatory site visit with WSA in order to participate in the second stage Request For Qualifications (RFQ) process. This project has many challenging logistical components which are outlined in this RFSQ.
No additional information for this competition.
Award Documents:
Award Details
Top Shot Concrete Inc.
$1,640,088.99
This price includes PST
Feb 21, 2020
Top Shot Concrete Inc.
|
|
$1,640,088.99
|
This price includes PST
|
Feb 21, 2020
|
|
Mar 20, 2020 11:38 AM CST
|
|
Aug 20, 2019 04:45 PM CST
|
|
Sep 10, 2019 04:00 PM CST
|
Ty Vallee
306-694-8945
ty.vallee@wsask.ca
Water Security Agency
101-111 Fairford Street East
MOOSE JAW SK S6H 7X9
Reference Number: WSA-2019-0112
Attention: Ty Vallee
Competition Information
Awarded
|
WSA-2019-0112
|
Water Security Agency
|
Request for Supplier Qualifications for Lac La Ronge Dam Seepage Remediation
|
Request for Qualifications
|
No
|