Town of Wynyard - Landfill RFQ -- TOW-064-052-RFQ

Construction of the first phase of a landfill, consisting of a single 0.8 hectare cell able to accommodate approximately 22,000 m3 of waste. This work will include the construction of a berm around the cell, drainage channels around the perimeter of the full buildout of the landfill, and a clay liner. Earthwork will include knowledge of using different types of subgrade materials in certain areas of construction totalling approximately 28,000 m3 of excavation. This includes 2,100 m3 Random Fill, 5,900 m3 Select Fill, 12,500 m3 Clay Liner, and 4,450 m3 Waste.

Installation of a leachate collection system comprised of 300 m of 150 mm leachate collection pipe running longitudinally beneath the centre of the landfill cell and terminating at an underground collection tank. Collection system will include installation of a manhole and cleanout.

Additional constructed items include a 180 m vehicle access ramp, fencing, topsoil replacement, and seeding.

RFQ documents can be obtained via Sharefile. Please contact Jon Kroeker to gain access to the Sharefile folder.

Competition Documents:
Amendment Documents:
 Mar 22, 2018 02:05 PM CST
 Mar 14, 2018 04:00 PM CST
 Mar 22, 2018 02:00 PM CST
Contact
Jon Kroeker
306-343-7280
j.kroeker@cwce.ca
Response Address
Catterall & Wright
1221 8th Street East
Saskatoon, SK
S7H 0S5
Competition Information
Closed
TOW-064-052-RFQ
Town of Wynyard
Town of Wynyard - Landfill RFQ
Request for Qualifications
No
The Competition detail was successfully retrieved. Apr 24, 2024 05:57 PM CST